Relief for Homebuyers
Chinnmay Shah 5 Nov 2020

Relief for Homebuyers

Big relief for homebuyers:
Supreme Court of India says the builder-buyer agreement must be considered as flat allotment date, not when the project got RERA registered.

Providing relief to thousands of homebuyers, the Supreme Court has ruled that the period of allotment of a housing unit to a homebuyer has to be considered from the date of the builder-buyer agreement and not from the date of registration of the project under the Real Estate (Regulation and Development) Act, 2016.

The builder-buyer agreement becomes effective upon signing and all obligations of the flat buyers get linked to the timelines set out in the builder-buyer agreement but developers all along have been taking undue benefit of a delayed RERA registration and linking their obligations with the RERA registration date said legal experts.

The court made the observation in a judgment in the case pertaining to M/S Imperia Structures Limited vs Anil Patni and another case by a division bench comprising Justices UU Lalit and Vineet Saran

Did you find this write up useful? YES 1 NO 0
×

C2RMTo Know More

Something Awesome Is In The Work

0

DAYS

0

HOURS

0

MINUTES

0

SECONDS

Sign-up and we will notify you of our launch.
We’ll also give some discount for your effort :)

* We won’t use your email for spam, just to notify you of our launch.
×

SAARTHTo Know More

Launching Soon : SAARTH, your complete client, case, practise & document management SAAS application with direct client chat feature.

If you want to know more give us a Call at :+91 98109 29455 or Mail info@soolegal.com