appellant was awarded the work order dated 20.07.1995 pursuant to a tender floated by the Respondent in 1994. The contract agreement was for the purpose of well drilling and other auxiliary operations in Assam, and the same was effectuated from 05.06.1996. Although, the contract was initially only for a period of two years, the same was extended for two successive periods of one year each by mutual agreement, and finally the contract expired on 04.10.2000.

3. During the subsistence of the contract, the prices of High­ Speed Diesel (“HSD”), one of the essential materials for carrying out the drilling operations, increased. Appellant raised a claim that increase in the price of HSD, an essential component for carrying out the contract triggered the “change in law” clause under the contract (i.e., Clause 23) and the

Respondent became liable to reimburse them for the same.

2

When the Respondent kept on rejecting the claim, the Appellant eventually invoked the arbitration clause vide letter dated 01.03.1999. The dispute was referred to an Arbitral Tribunal comprising of three arbitrators.

User Comments


×

C2RMTo Know More

Something Awesome Is In The Work

0

DAYS

0

HOURS

0

MINUTES

0

SECONDS

Sign-up and we will notify you of our launch.
We’ll also give some discount for your effort :)

* We won’t use your email for spam, just to notify you of our launch.
×

SAARTHTo Know More

Launching Soon : SAARTH, your complete client, case, practise & document management SAAS application with direct client chat feature.

If you want to know more give us a Call at :+91 98109 29455 or Mail info@soolegal.com